Construction Update - July 2026

County Road 68 Rockingham Road, Township of Brudenell, Lyndoch and Raglan

Construction Update – July 2, 2026

The Department of Public Works and Engineering provides monthly updates on construction projects within the County of Renfrew. Please share this notice to keep everyone informed of upcoming construction projects. Contact our office should you have any questions or concerns about County construction or general operations.

To review details and maps of all of the County’s 2026 construction plans, please visit the 2026 Construction Story Map at https://arcg.is/1K5Hnu1.

For up-to-date information on active projects and their traffic impacts, please visit Municipal511 at https://www.municipal511.ca/.

Upcoming Projects

County Roads 26 (Doran Road) – Township of Laurentian Valley

Construction on Doran Road, from Forest Lea Road to Highway 17, is expected to start July 6, 2026, and be completed late-August. During construction, parts of Doran Road will be limited to a single lane, with lights or workers directing traffic.

County Road 653 (Chenaux Road) – Township of Whitewater Region

Construction on Chenaux Road, from Highway 17 to Camp Galilee Lane, is expected to start July 3, 2026, and be completed late-August. To facilitate the replacement of a culvert, Chenaux Road will be closed between Highway 17 and Magnesium Road for approximately 2 weeks with a signed detour in place. During the remainder of the construction project, parts of Chenaux Road will be limited to a single lane, with lights or workers directing traffic.

County Structure B091 (Danny Constant Bridge) – Township of Bonnechere Valley

Construction on Danny Constant Bridge, on Constant Lake Road, about 1.8 kilometres west of Highway 41, is expected to start August 1, 2026, and be completed late-September. During construction, the road at this location will remain closed to all traffic, with a signed detour in place. There will be no pedestrian access during the project.

County Structure B103 (O’Grady Bridge) – Township of Killaloe, Hagarty and Richards

Construction on O’Grady Bridge, on O’Grady Settlement Road, about 5 kilometres west of Brudenell Road, is expected to start September 1, 2026, and be completed late-October. During construction, the road at this location will remain closed to all traffic, with a signed detour in place. There will be no pedestrian access during the project.

Ongoing Projects

County Roads 1 (River Road) and 20 (Castleford Road) – Township of Horton

Construction on River Road, from Castleford Road to Grantham Road, and Castleford Road, from River Road to Humphries Road, started June 15, 2026, and is expected to be completed early-August. During construction, parts of River Road and Castleford Road will be limited to a single lane, with lights or workers directing traffic.

County Roads 14 (Witt Road) – Township of Laurentian Valley

Construction on Witt Road, from County Road 56 (Woito Station Road) to County Road 26 (Doran Road), started June 29, 2026, and is expected to be completed early-September. During construction, parts of Witt Road will be limited to a single lane, with lights or workers directing traffic. Some multi-day road closures will be needed during the project; detours will be signed during these closures. 

County Road 68 (Rockingham Road) – Township of Brudenell, Lyndoch and Raglan

Construction on Rockingham Road, from Guiney Road to Letterkenny Road, started May 19, 2026, and is expected to finish late-July. During construction, parts of Rockingham Road will be limited to a single lane, with lights or workers directing traffic.

County Road 508 (Calabogie Road) – Townships of Greater Madawaska and McNab/Braeside

Brushing and culvert replacements have been completed with asphalt patching to occur during July. The remainder of construction on Calabogie Road, from Fleming Road to County Road 52 (Burnstown Road), is expected to start mid-August and be completed late-October. During construction, parts of Calabogie Road will be limited to a single lane, with lights or workers directing traffic.

County Structure B121 (Waba Creek Bridge) – Township of McNab/Braeside

Construction on Waba Creek Bridge, on White Lake Road, about 0.8 kilometres west of Highland Road, is expected to start July 2, 2026, and be completed early-September. During construction, the road at this location will be limited to a single lane of traffic during the day with workers directing traffic. For a period of six weeks between June 29th and August 28th, the road at this location will be closed to all traffic, with a signed detour in place. There will be no pedestrian access during the closure.

County Structure C201 (Broomes Creek Culvert & Dam) – Township of Whitewater Region

Construction on Broomes Creek Culvert and Dam, located on County Road 7 (Foresters Falls Road), about 0.1 kilometres east of Foresters Falls, resumed May 4, 2026, and is expected to be completed late-July. During construction, the road at this location will remain closed to all traffic, with a signed detour in place. There will be no pedestrian access during the closure.

Completed Projects

County Road 4 (Storyland Road) – Township of Horton

Construction on Storyland Road, from Eady Road to Alex Lane is carry-over work from last year. Construction was completed on July 2, 2026.

County Road 66 (Wilno South Road) – Townships of Killaloe, Hagarty and Richards and Madawaska Valley

Construction on Wilno South Road, from Highway 60 to Inukshuk Road, was completed on June 26, 2026, with only minor works and line painting remaining to be completed.

County Road 69 (Siberia Road) – Township of Madawaska Valley

Construction on Siberia Road, from Sunny Hill Road to Pipedream Lane, was completed on June 25, 2026, with only line painting remaining to be completed.

County Road 512 (Foymount Road) – Township of Bonnechere Valley

Construction on Foymount Road, from Silver Lake Road to Highway 41, was completed on June 26, 2026, with only minor works and line painting remaining to be completed.

For the safety of all, please use extra caution when travelling through construction zones

County Structure C201 (Broomes Creek Culvert & Dam), Township of Whitewater Region