Algonquin Trail in Laurentian Hills
The County of Renfrew’s Public Works and Engineering Department has provided monthly updates on construction in the area throughout the 2025 construction season. Please visit the link below to sign up to receive these updates by email: https://renfrew-county.civilspace.io/en/projects/2025-county-transportation-infrastructure-projects
Please share this notice so that residents, businesses, and others know about traffic delays from construction projects. For the latest details on current projects, and their traffic effect, please check Municipal511 at https://www.municipal511.ca/.
Completed Projects
2025 was overall a successful year for the Capital Works Division of the Public Works & Engineering Department, with many projects completed as highlighted below:
Other works to highlight in support of completing the above, and the County’s overall transportation network, include the below:
Ongoing Projects
County Road 4 (Storyland Road) – Township of Horton
Construction on Storyland Road, from Alex Lane to Highway 17, started September 22, 2025. Construction has been paused for the winter and will resume after the spring thaw in 2026.
County Road 71 (Matawatchan Rd.) – Township of Greater Madawaska
Rock removal and widening of the causeway is complete on Matawatchan Road, about 8.2km south of Highway 41. Utility relocations have also been completed, and road construction on Matawatchan Road, from Civic Address 4882 to Centennial Lake Road, continued in mid-October. Construction has been paused for the winter and will resume after the spring thaw in 2026.
County Road 512 (Foymount Road) – Township of Bonnechere Valley
Construction on Foymount Road, from Silver Lake Road to Highway 41, started September 8, 2025. Construction has been paused for the winter and will resume after the spring thaw in 2026.
County Structure B145 (Combermere Bridge) – Township of Madawaska Valley
Construction on Combermere Bridge, which is on Combermere Road, about 0.5km south of Palmer Road, started April 2, 2025, and is nearing completion with only minor works remaining. During construction, only one lane may be open to cross the bridge, with traffic control personnel directing traffic. Mill Street will be closed at Combermere Road during construction, with signs showing the detour route. Pedestrians can cross the bridge during construction. Once completed for the 2025 construction season, Mill Street will be opened, with only minor works expected in 2026 on the bridge.
County Structure C201 (Broomes Creek Culvert & Dam) – Township of Whitewater Region
Construction on Broomes Creek Culvert and Dam, which is on Foresters Falls Road, about 0.1km east of Foresters Falls, started May 1, 2025 and is expected to finish in 2026. Construction has been paused for the winter and will resume after the spring thaw in 2026. The road in this area will remain closed to all traffic, including pedestrians, with signs showing the detour route, until construction is completed in 2026. The detour will follow Kohlsmith Road and Queens Line.
THANK YOU FOR PATIENCE AND CARE THROUGHOUT 2025 WE LOOK FORWARD TO 2026!

County Structure C201 (Broomes Creek Culvert and Dam), Township of Whitewater Region