County Road 512 (Foymount Road) - Township of Bonnechere Valley
The County of Renfrew’s Public Works and Engineering Department provides monthly updates on construction in the area. Please visit the link below to sign up to receive these updates by email: https://renfrew-county.civilspace.io/en/projects/2025-county-transportation-infrastructure-projects
Please share this notice so that residents, businesses, and others know about traffic delays from construction projects. For the latest details on current projects, and their traffic effect, please check Municipal511 at https://www.municipal511.ca/.
Ongoing Projects
County Road 4 (Storyland Road) – Township of Horton
Construction on Storyland Road, from Alex Lane to Highway 17, started September 22, 2025 and is expected to finish mid-November. During construction, parts of Storyland Road will only have one lane open, with lights or workers directing traffic.
County Road 71 (Matawatchan Rd.) – Township of Greater Madawaska
Rock removal and widening of the causeway is complete on Matawatchan Road, about 8.2km south of Highway 41. Utility relocations have also been completed, and road construction on Matawatchan Road, from Civic Address 4882 to Centennial Lake Road, continued in mid-October and is expected to finish mid-November. During construction, areas of Matawatchan Road will only have one lane open, with lights or workers directing traffic.
County Road 512 (Foymount Road) – Township of Bonnechere Valley
Construction on Foymount Road, from Silver Lake Road to Highway 41, started September 8, 2025 and is expected to finish late-November. During construction, parts of Foymount Road will only have one lane open, with lights or workers directing traffic.
County Structure B122 (Waba Creek Bridge) – Township of McNab/Braeside
Construction on Waba Creek Bridge, which is on Burnstown Road, about 0.7 km north of White Lake Road, started July 14, 2025 and is expected to finish late-November. During construction, only one lane will be open to cross the bridge, with signals directing traffic. Pedestrians can cross the bridge during construction.
County Structure B145 (Combermere Bridge) – Township of Madawaska Valley
Construction on Combermere Bridge, which is on Combermere Road, about 0.5km south of Palmer Road, started April 2, 2025 and is expected to finish mid-November. During construction, only one lane will be open to cross the bridge, with signals directing traffic. Mill Street will be closed at Combermere Road during construction, with signs showing the detour route. Pedestrians can cross the bridge during construction.
County Structure C201 (Broomes Creek Culvert & Dam) – Township of Whitewater Region
Construction on Broomes Creek Culvert and Dam, which is on Foresters Falls Road, about 0.1km east of Foresters Falls, started May 1, 2025 and is expected to finish in 2026, with a stoppage over winter. During construction, and over the winter, the road in this area will be closed to all traffic, including pedestrians, with signs showing the detour route. The detour will follow Kohlsmith Road and Queens Line. For more details on this project, please visit: https://renfrew-county.civilspace.io/en/projects/c201-broomes-creek-culvert-dam-reconstruction
Algonquin Trail – Township of Head, Clara and Maria
Construction on Algonquin Trail, from Yates Road to Crossing Road, started September 29, 2025 and will finish late-November. Stone dust surface is also being applied from Mackey Creek Road to Yates Road. These sections of Algonquin Trail will remain closed until late 2025 once construction, including signage installation is completed.
Completed Projects
County Road 20 (Castleford Road) – Township of Horton
Construction on Castleford Road, from Highway 17 to Humphries Road, started August 25, 2025 and is nearly complete, with only shoulder sealing and line painting remaining to be completed.
County Road 26 (Doran Road) – Town of Petawawa
Construction on Doran Road, from Black Bay Road to Petawawa Boulevard, started July 22, 2025 and is nearly complete, with only line painting, minor sidewalk works, and a pedestrian crosswalk remaining to be completed.
County Road 52 (Burnstown Road) and 508 (Calabogie Road) – Township of McNab/Braeside
Construction on Burnstown Road, from the Burnstown Bridge to Picket Hill Lane, and on Calabogie Road from Stacey Drive to 1803 Calabogie Road, started August 11, 2025 and was completed October 17, 2025.
County Road 512 (Foymount Road) – Township of Bonnechere Valley
Construction on Foymount Road, from Quadeville Road to McCauley Mount Road, started August 11, 2025 and finished September 29, 2025.
C134 (Campbell Drive Culvert) – Township of McNab/Braeside
Construction for slope stabilization at Campbell Drive Culvert, on Campbell Drive, approximately 2.4km north of Highway 417, started on October 6, 2025 and finished on November 4, 2025. Hydroseeding remains to be completed; at which time the roadway will be limited to a single lane of traffic with lights or workers directing traffic.
PLEASE DRIVE WITH CARE THROUGH CONSTRUCTION SITES THANK YOU FOR PATIENCE